Our scrummer#FAIL project was moving swiftly though troubled waters towards imminent failure, and the attention our project was getting inside the organization was increasing: senior managers thought that they should get more involved, some to reduce risks, some others just to cover their asses. This management involvement was making a difficult task almost impossible.
First, we got the auditors. They all came in because the managers didn't understand what the project was doing and they thought that maybe somebody external could give us better ideas. Nice thought, but that dramatically increased the number of meetings and the time wasting explaining just another time what the project was all about and why people where doing what they were doing. The result of the audits was mostly positive, with some recommendations the auditors had to write to show that there is space for improvement (isn't there always such a thing?).
Then, we got the senior managers sitting on our laps. They wanted to know why in god's name everybody was wasting a day every two weeks just to talk. Wouldn't it be possible to use that time more effectively? If developers would use that time to code and testers to test, all the problems would be gone, right?
WRONG!
"Could we reduce the time assigned to the Sprint Planning Meeting from 4 hours to just 1 hour? That would give us 3 hours every two weeks, roughly 6 hours a month, multiplied by 100 people, we are talking about 600 man-hours per month."
WRONG!
"Ok, and let's talk about the retrospectives - I mean, if we do a retrospective every 2nd or 3rd Sprint, that would save us - let me just create a small excel sheet..."
SO TERRIBLY WRONG!
So we had to start from the basics, and explain how important it was that everyone actually understood what we were doing and why we were doing it. We explained how the requirements where formulated as stories and discussed with the team, we discussed about self-management, we discussed, we discussed, we discussed.
The issue about the scrummer#FAIL period we are living is that organizations are partially agile and partially industrial age behemoths. They are filled with people who learned Scientific Management and with habits which come from those times where polluting factories where good factories. And they have pockets of agility, teams of motivated people working focused, together, pragmatically towards the same goal. This dichotomy is sometimes worse than any of those two worlds, because instead of harnessing the power of those two different worlds, it produces a nasty combination of disadvantages. A world of misunderstandings, of miscommunication. A fight of philosophies which paralyzes organizations in fruitless discussions.
Before all that management involvement, the project was trying to deliver software. When that involvement started, the project was just talking to managers and forgot about the software.
Real-life stories about the hard life in projects combining Scrum and Waterfall mindsets
Thursday, December 11, 2014
Wednesday, December 10, 2014
Just make it updatable!
Development of our system started following a clearly undefined Scrummer#FAIL process. A Waterfall-minded project had a small, but growing, Scrum heart. They were producing and delivering tested increments of software every two weeks. The project was still in an early phase and the plan was to deliver it (use it in Production) in more than six months time. The reason behind that was mostly internal bureaucracy, but that's another story.
Now in that stage, the system was under heavy development which meant that even the database schema was being extended and modified frequently. Fortunately, the team was able to convince Michael, our Project Manager, to keep extending the database incrementally, to match the methodology used to develop the software. It was not humanly possible to define the whole database schema upfront, as future requirements where not clear.
But the development on this project had to coexist with a detailed block plan which defined the rhythm of testing, documentation, training and many other activities. At a certain point in time, it was required to create a massive test environment and use it for a testing phase which lasted for several weeks. Doing such a long testing phase in a development project which was delivering new versions every two weeks was seen as ridiculous, but it had to be. So our project manager decided that the system had to be updated every week and that all data had to be kept in the system (migrated) during the updates.
That was all possible, but not an easy task at that stage. A meeting was setup to talk about that database migration procedure. It was important to determine the cost of that development and the possible impact that could have in the project schedule. The list of attendees to that meeting was long. Way too long for a technical discussion. Many managers, software developers and our Project Manager attended the meeting. Oh, and also many more managers.
The discussion started to drift towards deeper and deeper technical waters and Michael, our Project Manager, started to get nervous. He stopped the collaboration route and switched towards the "I expect" route. He told the group that he couldn't understand why such a discussion was needed simply to turn on the "Updatability flag" on the software. Our software developers were polite and didn't laugh. But they also didn't know what to say. For them, it was obvious that a functionality had to be developed before it can be "turned on".
But the truth is, that the incident uncovered an important problem: the Project Manager didn't understand what was being done and what effort things implied. That deep knowledge gap between "decision makers" and IT-experts was going to produce us many more headaches...
Read "HELP! Our managers are coming to help us!"...
Now in that stage, the system was under heavy development which meant that even the database schema was being extended and modified frequently. Fortunately, the team was able to convince Michael, our Project Manager, to keep extending the database incrementally, to match the methodology used to develop the software. It was not humanly possible to define the whole database schema upfront, as future requirements where not clear.
But the development on this project had to coexist with a detailed block plan which defined the rhythm of testing, documentation, training and many other activities. At a certain point in time, it was required to create a massive test environment and use it for a testing phase which lasted for several weeks. Doing such a long testing phase in a development project which was delivering new versions every two weeks was seen as ridiculous, but it had to be. So our project manager decided that the system had to be updated every week and that all data had to be kept in the system (migrated) during the updates.
That was all possible, but not an easy task at that stage. A meeting was setup to talk about that database migration procedure. It was important to determine the cost of that development and the possible impact that could have in the project schedule. The list of attendees to that meeting was long. Way too long for a technical discussion. Many managers, software developers and our Project Manager attended the meeting. Oh, and also many more managers.
The discussion started to drift towards deeper and deeper technical waters and Michael, our Project Manager, started to get nervous. He stopped the collaboration route and switched towards the "I expect" route. He told the group that he couldn't understand why such a discussion was needed simply to turn on the "Updatability flag" on the software. Our software developers were polite and didn't laugh. But they also didn't know what to say. For them, it was obvious that a functionality had to be developed before it can be "turned on".
But the truth is, that the incident uncovered an important problem: the Project Manager didn't understand what was being done and what effort things implied. That deep knowledge gap between "decision makers" and IT-experts was going to produce us many more headaches...
Read "HELP! Our managers are coming to help us!"...
Heinz only Shows Green
Heinz is a nice guy. Very reserved, he had spent the last 30 years slowly but surely climbing the hierarchy ladders of the corporation. He was always convinced that quality was the driver for success in a corporation and as such, he was known and admired for the perfection of his work. He knew he was smart, and he did seldom listen to others.
The recipe used by his fellow colleagues to climb the ladders was less idealistic, but way more effective. Some of the people who used to work under his position were now many levels higher than him on the org chart. They didn't deliver so much, they didn't strive for perfection, but they could sell themselves and their results much better than Heinz.
He was now in his late fifties, on the final straight towards retirement. The only thing he needed was a promotion, to retire in glory, to get enough money for a luxurious living. He knew that his career climb had been too slow, and had now that ambition, that goal in mind, and was keen to try everything possible to get there.
In our Scrummer#FAIL project, he got the Product Owner title for a business area he understood - he had the technical expertise roughly in that area some years ago. Now he had a team of people representing the business reporting to him, and a bigger team of software developers and testers who were going to develop whatever he gave them to do. And they all had to do Scrum.
He didn't hide the fact that he didn't understand software development. But he couldn't imagine that he would be responsible for the delivery of a product without controlling the work every developer did. He knew that he couldn't manage that big group of people, but he felt that he had to command-and-control them.
After some Sprints, the team was making progress in spite of his attempts to dictate how they had to do their work, but it was painful. Again and again, he blamed his team for things which went wrong, and fought to hide anything which could be seen as failure.
I remember one day, during the preparations for our Sprint Review Meeting, we asked his team what they were going to show during the meeting, and they said "nothing". They didn't want to show stuff, because it was not "done". In those meetings, we also showed a high-level summary slide containing the stories committed by each team, and marked them with different colors, depending on the result. Well, our Heinz wanted to have everything green, even though the team was saying that nothing was "done".
That opened an interesting discussion which lasted for almost a day. We had a definition of done, but our Product Owner silently decided to start using his own definition to show green. He even had some secret meetings with developers where he tried to convince them to mark the stories as done and develop some functionality which was obviously missing in a later stage, to hide the fact that some things were not done.
He didn't understand the meaning of "red". His ambition was blinding him and he was pushing his team to hide stuff under the carpet. All of our attempts to stop him from doing that, were not enough to avoid some "surprises" we discovered shortly before the system went live.
I like him and I admire his trajectory. Nevertheless, I know that he was not the right man for the job.
Also read this (real-life) story: "Just make it updatable!"...
The recipe used by his fellow colleagues to climb the ladders was less idealistic, but way more effective. Some of the people who used to work under his position were now many levels higher than him on the org chart. They didn't deliver so much, they didn't strive for perfection, but they could sell themselves and their results much better than Heinz.
He was now in his late fifties, on the final straight towards retirement. The only thing he needed was a promotion, to retire in glory, to get enough money for a luxurious living. He knew that his career climb had been too slow, and had now that ambition, that goal in mind, and was keen to try everything possible to get there.
In our Scrummer#FAIL project, he got the Product Owner title for a business area he understood - he had the technical expertise roughly in that area some years ago. Now he had a team of people representing the business reporting to him, and a bigger team of software developers and testers who were going to develop whatever he gave them to do. And they all had to do Scrum.
He didn't hide the fact that he didn't understand software development. But he couldn't imagine that he would be responsible for the delivery of a product without controlling the work every developer did. He knew that he couldn't manage that big group of people, but he felt that he had to command-and-control them.
After some Sprints, the team was making progress in spite of his attempts to dictate how they had to do their work, but it was painful. Again and again, he blamed his team for things which went wrong, and fought to hide anything which could be seen as failure.
I remember one day, during the preparations for our Sprint Review Meeting, we asked his team what they were going to show during the meeting, and they said "nothing". They didn't want to show stuff, because it was not "done". In those meetings, we also showed a high-level summary slide containing the stories committed by each team, and marked them with different colors, depending on the result. Well, our Heinz wanted to have everything green, even though the team was saying that nothing was "done".
That opened an interesting discussion which lasted for almost a day. We had a definition of done, but our Product Owner silently decided to start using his own definition to show green. He even had some secret meetings with developers where he tried to convince them to mark the stories as done and develop some functionality which was obviously missing in a later stage, to hide the fact that some things were not done.
He didn't understand the meaning of "red". His ambition was blinding him and he was pushing his team to hide stuff under the carpet. All of our attempts to stop him from doing that, were not enough to avoid some "surprises" we discovered shortly before the system went live.
I like him and I admire his trajectory. Nevertheless, I know that he was not the right man for the job.
Also read this (real-life) story: "Just make it updatable!"...
The Meeting Proficiency Assessment
Around the project there was a lot of talk about productivity. Everyone knew that the project was at risk because the goals where way too high, and people started to get nervous. We lived in a Scrummer#FAIL world, it was a waterfall project with some Scrum teams working in it's core. The cultures of these two worlds were just too different, and understanding between them was just an illusion.
People were looking at the Scrum rituals like for example the daily scrum meetings and the sprint review, retrospective and planning meetings and thought that it was a waste of time having highly paid IT experts just sitting and talking. They had the idea that software developers were like machines who translate functional specifications into code - the longer the better, of course.
Managers from many different teams started debating about how efficient that was. Even though non of them had any background on software development or in managing such projects, they had strong opinions and where willing to defend them. They hadn't even read any books written about the topic in the last 20 years, so you can imagine how basic those discussions were.
Luckily, there was an organisational development guru around and he was asked by our Project Management to asses the meeting proficiency of all teams around the project. The guy visited all meetings around the project for several days and communicated his verdict to the Project Management. His result was that most meetings around where unproductive, they didn't let everyone to give their opinions, they were not properly prepared and very badly moderated. There was just one exception: the meetings held by those Scrum Freaks. The meetings they held were short, they had a clear topic and were organized in a way that let everyone participate.
For good or for bad, that was the day where people from all different parts of the project started doing standup meetings. It's great to see good practices adopted, it's scary when people do it without understanding why.
Read "Heinz only Shows Green"...
People were looking at the Scrum rituals like for example the daily scrum meetings and the sprint review, retrospective and planning meetings and thought that it was a waste of time having highly paid IT experts just sitting and talking. They had the idea that software developers were like machines who translate functional specifications into code - the longer the better, of course.
Managers from many different teams started debating about how efficient that was. Even though non of them had any background on software development or in managing such projects, they had strong opinions and where willing to defend them. They hadn't even read any books written about the topic in the last 20 years, so you can imagine how basic those discussions were.
Luckily, there was an organisational development guru around and he was asked by our Project Management to asses the meeting proficiency of all teams around the project. The guy visited all meetings around the project for several days and communicated his verdict to the Project Management. His result was that most meetings around where unproductive, they didn't let everyone to give their opinions, they were not properly prepared and very badly moderated. There was just one exception: the meetings held by those Scrum Freaks. The meetings they held were short, they had a clear topic and were organized in a way that let everyone participate.
For good or for bad, that was the day where people from all different parts of the project started doing standup meetings. It's great to see good practices adopted, it's scary when people do it without understanding why.
Read "Heinz only Shows Green"...
The day Igor the Great dictated himself into Insignificance
After many issues and discussions, Michael, our project manager understood that the project had a problem with the middle management. Almost all of them were young, ambitious and unexperienced. Most of them managed people for the first time and did not because they liked it, but because it was a career opportunity. After hearing them moaning and complaining about the project, and about poor results of some teams, Michael decided that it was a good idea to give those managers more power. His reasoning was smart: he thought that if they get more freedom, they have less space to complain about.
They were given the "Product Owner" role for their business areas. And they were forced to accept ownership and to be accountable for the results of what their "Scrum Teams" were going to produce.
This is where things really started to fall apart.
The new "Product Owners" were scared. They didn't understand software development, they couldn't spell the word "Scrum" (they just knew that it was something evil) and even though they were leading some business areas, they didn't really understand the business. And now they would be responsible for what a bunch of chaotic developers would produce? That was the plan.
I remember a discussion with Igor, one of the newly defined Product Owners. He was a young guy, coming from one of the business areas, known by his harsh, and almost militaristic way ofleading commanding people. A week after the announcement that he was going to be the owner of one part of the system, he produced a detailed plan of what each developer was going to do, day by day, for the next two and a half months. He showed me the plan, and explained me that it was very important to have that plan to monitor the progress and to be able to identify the culprit if things went wrong. At the beginning I thought he was joking, but he was dead serious.
Twenty minutes later, he was still showing me the intricacies of his plan and I was still petrified, unable to formulate a sentence to tell this poor chap that all the time he had spent during the last week was wasted, that it would never work. Ah and that by the way, he shouldn't be focused on preparing a plan to blame someone else in case of failure. I don't remember having many such moments where you just don't know how to start explaining something, but that was a candidate for the top 1.
There must have been something in my face that was shouting that everything was so wrong. He stopped talking and there was a long and deep silence until I said: "Igor, you have worked a lot on this, I can see it". It didn't take long until he had to admit that he didn't have any experience with software development. So I spent the next 3 hours explaining him why it wouldn't make sense to do a detailed plan for the next months, and why he should focus on requirements and priorities and his team should figure out how to make that work. I was pleased that he listened and he acknowledged during the chat, that things were going in the right direction. I told him that I could help him to produce a backlog of the features he wanted the team to build.
But that was the first an last time somebody saw him listening to someone during the project. His command-and-control mindset was so deeply burnt in his personality, that he couldn't stop acting as a dictator and telling everyone what they should do, until it happened that everybody stopped listening to him. It was a tragic figure, but we saw him coming every morning, saying hello to everyone and then he sat down in front of his laptop and looked busy. Nobody ever knew what he was doing. I think that he understood that the project would run better without him, so he just came in every morning and tried not to interfere.
That was so sad, but having Igor, the manager and newly defined Product Owner away from the team helped to dramatically increase motivation and thus productivity.
Read "The Meeting Proficiency Assessment"...
They were given the "Product Owner" role for their business areas. And they were forced to accept ownership and to be accountable for the results of what their "Scrum Teams" were going to produce.
This is where things really started to fall apart.
The new "Product Owners" were scared. They didn't understand software development, they couldn't spell the word "Scrum" (they just knew that it was something evil) and even though they were leading some business areas, they didn't really understand the business. And now they would be responsible for what a bunch of chaotic developers would produce? That was the plan.
I remember a discussion with Igor, one of the newly defined Product Owners. He was a young guy, coming from one of the business areas, known by his harsh, and almost militaristic way of
Twenty minutes later, he was still showing me the intricacies of his plan and I was still petrified, unable to formulate a sentence to tell this poor chap that all the time he had spent during the last week was wasted, that it would never work. Ah and that by the way, he shouldn't be focused on preparing a plan to blame someone else in case of failure. I don't remember having many such moments where you just don't know how to start explaining something, but that was a candidate for the top 1.
There must have been something in my face that was shouting that everything was so wrong. He stopped talking and there was a long and deep silence until I said: "Igor, you have worked a lot on this, I can see it". It didn't take long until he had to admit that he didn't have any experience with software development. So I spent the next 3 hours explaining him why it wouldn't make sense to do a detailed plan for the next months, and why he should focus on requirements and priorities and his team should figure out how to make that work. I was pleased that he listened and he acknowledged during the chat, that things were going in the right direction. I told him that I could help him to produce a backlog of the features he wanted the team to build.
But that was the first an last time somebody saw him listening to someone during the project. His command-and-control mindset was so deeply burnt in his personality, that he couldn't stop acting as a dictator and telling everyone what they should do, until it happened that everybody stopped listening to him. It was a tragic figure, but we saw him coming every morning, saying hello to everyone and then he sat down in front of his laptop and looked busy. Nobody ever knew what he was doing. I think that he understood that the project would run better without him, so he just came in every morning and tried not to interfere.
That was so sad, but having Igor, the manager and newly defined Product Owner away from the team helped to dramatically increase motivation and thus productivity.
Read "The Meeting Proficiency Assessment"...
Red is so Evil
Michael, our Project Manager, came to me just before the Review Meeting. He wanted to see the slides I was going to show during my presentation. Today we were going to have some senior managers visiting the project and he wanted to make sure that we were not going to say or show anything wrong. I opened the slides and showed him the results of our work during the last two weeks (a Sprint, using the Scrum terminology). He was shocked! So much red!
We did our Review Meetings in a big auditorium which was embedded in our open-plan office. Everybody who was walking to the coffee machine could see what we were presenting, and that was on purpose. We wanted to share our status, we wanted everybody to know where we were and the difficulties we faced. We wanted that, but Michael, our Project Manager, preferred to "translate" the message to something he believed the senior management could digest better. It was his own version of reality.
In our terms, his reality was a lie, and lies were our enemy. We worked in iterations and it was critical for us to detect our mistakes to overcome them. Sweeping our failure under the carpet wouldn't help us to improve, we wanted to try things instead of discussing them forever. We wanted to fail early, to discover how to do it right. Detecting that we didn't achieve a self-imposed deadline in a two week period saddened us, because of all the energy we invested. But that information was for us a powerful tool to improve, and make the next two weeks much better. For Michael it was different. He wanted to comply with the unwritten rules of the organization: "if you show RED to your boss, he will intervene and things will get ugly".
Well, our transparency and his obfuscation didn't go well together. He tried to convince me to make the slides greener or at least to change red by orange. I had to laugh. That was so childish, but I knew that it was a true problem and I knew how common such issues were. Industrial age organizations don't want to see the truth, they prefer to communicate expectations and hide failure. Our little development team followed information age values and principles: we couldn't produce without being transparent, we couldn't self-organize without trust.
I showed the slide with lots of red and i could almost hear the bomb exploding. Some faces paled, some others showed that they would soon explode out of anger. There were many crisis meetings after that day, and maybe somebodies job was at risk. But it helped us to talk about things which were going very wrong and we could fix them on time.
But it was not the last time I had to discuss with Michael about our "disease of showing red all the time".
And it get's better - read "The day Igor the Great dictated himself into Insignificance"...
We did our Review Meetings in a big auditorium which was embedded in our open-plan office. Everybody who was walking to the coffee machine could see what we were presenting, and that was on purpose. We wanted to share our status, we wanted everybody to know where we were and the difficulties we faced. We wanted that, but Michael, our Project Manager, preferred to "translate" the message to something he believed the senior management could digest better. It was his own version of reality.
In our terms, his reality was a lie, and lies were our enemy. We worked in iterations and it was critical for us to detect our mistakes to overcome them. Sweeping our failure under the carpet wouldn't help us to improve, we wanted to try things instead of discussing them forever. We wanted to fail early, to discover how to do it right. Detecting that we didn't achieve a self-imposed deadline in a two week period saddened us, because of all the energy we invested. But that information was for us a powerful tool to improve, and make the next two weeks much better. For Michael it was different. He wanted to comply with the unwritten rules of the organization: "if you show RED to your boss, he will intervene and things will get ugly".
Well, our transparency and his obfuscation didn't go well together. He tried to convince me to make the slides greener or at least to change red by orange. I had to laugh. That was so childish, but I knew that it was a true problem and I knew how common such issues were. Industrial age organizations don't want to see the truth, they prefer to communicate expectations and hide failure. Our little development team followed information age values and principles: we couldn't produce without being transparent, we couldn't self-organize without trust.
I showed the slide with lots of red and i could almost hear the bomb exploding. Some faces paled, some others showed that they would soon explode out of anger. There were many crisis meetings after that day, and maybe somebodies job was at risk. But it helped us to talk about things which were going very wrong and we could fix them on time.
But it was not the last time I had to discuss with Michael about our "disease of showing red all the time".
And it get's better - read "The day Igor the Great dictated himself into Insignificance"...
End-to-End Testing
The block plan said that Cycle 1 Testing had to start on Monday. That phase was defined as an end-to-end test, which means that the whole system, including all interfaces and screens had to be checked by a big group of end-users. The PMO (Project Management Office) was working hard to arrange all travel plans and schedules for all participants. They were setting up the reporting and all the managers were busy jumping from meeting to meeting to get everything prepared.
And there was a small team of developers working on the most important and complex part of the system. Those developers were working in isolation and following a different schedule. They were using an iterative and incremental process. They were using Scrum in a Waterfall environment. They were doing Scrummerfall or Scrummer#FAIL.
The team, composed mostly of software developers, was delivering new functionality at a two week schedule. They had a list of features to build which was sorted by business value (they called it Product Backlog) and as soon as they had a piece developed and tested, they all worked on the next feature. They switched to this way of working after trying for several months to develop the software following cryptic, badly written functional specifications which didn't really contain the information needed to develop a system. The project accepted them to use that approach, without really understanding the implications.
And then, suddenly it happened that Cycle 1 Testing had to start. It was stated in the block plan, it had to happen! People were finishing test scripts. Those scripts contained detailed steps which had to be run by business representatives to test complete business processes with the new system. Reports were made to monitor the progress of the testing team during the two week testing period.
Monday came, and all those business representatives arrived from different countries and sat together on a big kick-off meeting. They were told about the testing procedures, about environments and about how to document their test results. And they started testing.
Some hours later, the first reports were produced. Testing had started and some issues were found. At the afternoon, a shocker: testing couldn't continue, because the scenarios the testers were running had important issues. Some of the functionality they had to test was not yet developed!
A crisis meeting was set up. The managers sat in the conference room and discussed about how to deal with this tragic situation. The development team was not delivering as it should and that had to be fixed right away. The whole project was failing because of their inability to deliver at a proper speed. That was the general opinion of most managers in the round, but they didn't really know how to fix it.
The problem was not the development team or the developers. The problem was the plan and the organization. It gave to different, isolated groups of people tasks which were not coordinated, and which didn't give the incentive of working together towards the same common goal. But that was the elephant in the room, the truth nobody could really see.
So after hours of thinking and debating, there was at last a plan. The project needed more developers. They had to work faster - and that iterative working thing had to be looked in detail, it looks like developers were wasting too much time talking in retrospective meetings instead of sitting in front of their computers and coding.
Michael, our project manager came to me to tell me the "good news". At last they had found the solution for our problem, we just had to get more developers and everything would be fine. I was amazed by the fact that he really believed in what he was saying and for me it was so wrong. The solution was not to add more horsepower to the "machine" doing the coding, to deliver the system, the whole "factory" had to be reengineered.
If the developers continued to work in isolation, just getting some documents from some other teams, producing software and throwing it to other teams to test, it wouldn't work. We had to put everyone together, and let them deliver software piece by piece. The plan had to be completely changed. I told Michael about that but he told me I was wrong. He said that the project plan was the source of truth, it told everybody what had to be done when and nobody would change the plan. Besides that, we were already on Wave 9, it was the ninth time the company had to work on something like this, and the plan, which was a copy-paste from Wave 8 was proven to succeed. No time to do experiments.
Interviews for at least 10 new software developers had to start next week. For me, that was a frustrating day.
But there is more... read "Red is so Evil"!
And there was a small team of developers working on the most important and complex part of the system. Those developers were working in isolation and following a different schedule. They were using an iterative and incremental process. They were using Scrum in a Waterfall environment. They were doing Scrummerfall or Scrummer#FAIL.
The team, composed mostly of software developers, was delivering new functionality at a two week schedule. They had a list of features to build which was sorted by business value (they called it Product Backlog) and as soon as they had a piece developed and tested, they all worked on the next feature. They switched to this way of working after trying for several months to develop the software following cryptic, badly written functional specifications which didn't really contain the information needed to develop a system. The project accepted them to use that approach, without really understanding the implications.
And then, suddenly it happened that Cycle 1 Testing had to start. It was stated in the block plan, it had to happen! People were finishing test scripts. Those scripts contained detailed steps which had to be run by business representatives to test complete business processes with the new system. Reports were made to monitor the progress of the testing team during the two week testing period.
Monday came, and all those business representatives arrived from different countries and sat together on a big kick-off meeting. They were told about the testing procedures, about environments and about how to document their test results. And they started testing.
Some hours later, the first reports were produced. Testing had started and some issues were found. At the afternoon, a shocker: testing couldn't continue, because the scenarios the testers were running had important issues. Some of the functionality they had to test was not yet developed!
A crisis meeting was set up. The managers sat in the conference room and discussed about how to deal with this tragic situation. The development team was not delivering as it should and that had to be fixed right away. The whole project was failing because of their inability to deliver at a proper speed. That was the general opinion of most managers in the round, but they didn't really know how to fix it.
The problem was not the development team or the developers. The problem was the plan and the organization. It gave to different, isolated groups of people tasks which were not coordinated, and which didn't give the incentive of working together towards the same common goal. But that was the elephant in the room, the truth nobody could really see.
So after hours of thinking and debating, there was at last a plan. The project needed more developers. They had to work faster - and that iterative working thing had to be looked in detail, it looks like developers were wasting too much time talking in retrospective meetings instead of sitting in front of their computers and coding.
Michael, our project manager came to me to tell me the "good news". At last they had found the solution for our problem, we just had to get more developers and everything would be fine. I was amazed by the fact that he really believed in what he was saying and for me it was so wrong. The solution was not to add more horsepower to the "machine" doing the coding, to deliver the system, the whole "factory" had to be reengineered.
If the developers continued to work in isolation, just getting some documents from some other teams, producing software and throwing it to other teams to test, it wouldn't work. We had to put everyone together, and let them deliver software piece by piece. The plan had to be completely changed. I told Michael about that but he told me I was wrong. He said that the project plan was the source of truth, it told everybody what had to be done when and nobody would change the plan. Besides that, we were already on Wave 9, it was the ninth time the company had to work on something like this, and the plan, which was a copy-paste from Wave 8 was proven to succeed. No time to do experiments.
Interviews for at least 10 new software developers had to start next week. For me, that was a frustrating day.
But there is more... read "Red is so Evil"!
The Bus
Michael, our project manager was looking worried. He was standing at a corner of our big, gray open-plan office looking at all those desks, all the people, and talking to some managers. He was worried because the project was running late and he was preparing his mind to give the bad news to the steering committee members next week. He was trying to figure out the right way to sell the message: the project was late but still progressing and worth the investment. He had to win the trust of the senior managers. He had to be prepared for their questions.
On previous waves, the project managers had used the same tactic of changing the bus schedule, Michael told me. And it worked. People had to work hard and long, but they were happy to deliver the system at the end. Steering committee members were already asking for it, they were questioning the ability of the project manager to take unpopular decisions. Besides that, having people working an hour more would increase productivity by around 12,5%!
Read "End-to-End Testing"...
The project offices were inside the compound of a massive factory, where a big warehouse was temporarily converted into office space to house around a hundred and fifty IT professionals from all over the world. The space was gray and didn't have windows, but it offered a good and flexible environment for efficient collaboration. The factory was a ten minutes drive from the nearest city and there were shuttle buses organized to pick everybody up from their hotels in the morning and to bring them back each afternoon. Working like that felt a little awkward at the beginning - it was like a downgrade in terms of liberty. All those high skilled IT professionals looked like an information age reincarnation of coal miners or other factory workers of the industrial revolution. They were carried in and out of the factory. But after some weeks, everybody got used to it. The system was comfortable and safe.
And then, it happened again. Michael came to me, and told me that we had to talk about the bus schedule. He wanted to change the time for the evening bus from 6pm to 7pm, to speed up the development. That was one of the changes he was going to communicate on the next steering committee meeting.
It was not the first time the company had made a project like this. In fact, they made them quite regularly, every second or third year. It was about extending the IT systems to cover more and more business processes. And they did it in a pulsing manner, they called these pulses "waves". So we were on Wave 9, and we had some veterans who had survived many of the previous waves. Those survivors were proud of their past and they remembered how hard they had to work to successfully deliver the previous projects.
On previous waves, the project managers had used the same tactic of changing the bus schedule, Michael told me. And it worked. People had to work hard and long, but they were happy to deliver the system at the end. Steering committee members were already asking for it, they were questioning the ability of the project manager to take unpopular decisions. Besides that, having people working an hour more would increase productivity by around 12,5%!
It was not the first time that I discussed with him about this, the first time I heard him talking about that idea, I thought he was joking. I took him to a quiet place in our auditorium, took a deep breath and started talking about intrinsic motivation. I told him that people needed a purpose and a proper environment and that they would do anything possible to deliver something good. I said that it would be better to give them all the information and let them take the right decisions rather than pushing them to do something without telling them why.
But as I was speaking, something inside me was slowly understanding that the gap between us was bigger and deeper than I initially thought. I was speaking on a language he was not able to understand. I was speaking in "informationish" and he was listening in "industrialish". For him, it was about man-hours and lines of code. For me, it was about hearts and produced value.
I used many words, drew many diagrams, but finally I lost the battle. The bus schedule was changed. People came to me afterwards and told me the change was silly. I had to agree. Some of them left earlier that day, they took a taxi.
That day I learnt that we are in the middle of a change from industrial revolution mindset towards an information age thinking, and that the gap between those eras can be bigger than my ability to sell ideas.
That day I learnt that we are in the middle of a change from industrial revolution mindset towards an information age thinking, and that the gap between those eras can be bigger than my ability to sell ideas.
Read "End-to-End Testing"...
Introduction
The name Scrummer#FAIL comes from ScrummerFALL, which is like the mix of the words "Scrum" and "Waterfall". Those words are commonly used in the world of software development to name the ways organizations use to build software.
Waterfall is the classical way to do software, it has been used for centuries (well, at least it feels like that). The approach is simple, it's an idea taken from manufacturing and follows the thinking of the industrial revolution: the assembly line. It requires to have separate groups of specialists who take some input, process it and pass it on to the next group. Each group tries to reduce the time it takes to get an input and pass it to the next group. Each group invests time and effort improving the quality of it's output. For a manager, this looks perfect. Optimizations at each step, it's measurable, transparent and responsibilities are clear. What else could you wish? That's why this kind of process was adopted in software development and is still widely used in most companies.
With time, waterfall started to morph into a sort of Frankenstein of the software development world. Managers were adding more and more metrics (they call them KPI's) to optimize it, to squeeze every bit of efficiency they could find in each of the phases. They felt that something was wrong and they tried to fix the symptoms they were finding. They even came with new ideas like overlapping those phases and having people to work on many of those at the same time to further increase efficiency. And that didn't help. Projects were still late, they still did not meet the expectations of the customers.
But people working in those processes where the ones who suffered the most. They knew that it was all going in the wrong direction. They felt that they were wasting their times, that they were not using their skills, that they were just pushing some buttons and could not use their instincts and their skills to move things forward. That was the birthplace of the "Agile Manifesto" and the start of a movement which today sells training and certifications to managers who still don't understand what they are buying. One of those products being sold today is called Scrum (tm). Gurus say that it's a framework, and what they mean by that is that you have to understand what you are doing instead of just following what people or books tell you to do.
Scrum talks about self-organization, about working in short time-slices (they call them sprints), about organizing the work to do in one single master list called a backlog. They say that you have to scrap your big master plan and start planning as you go. They say that you have to start using your brain and following what you believe is right. Scrum is a brand for all the ideas and principles behind the Agile Manifesto and the Lean movement. And it sells pretty good.
The ideas behind Agile and thus behind Scrum represent the thinking of the information age. Shared economy, empowerment, transparency, intrinsic motivation and many others. And here is where the tragedy starts. These ideas are completely opposite to the ones which currently build the culture of corporations. Trying to get enterprises to understand and follow these principles and these ways of working is the challenge of our generation, and it generates funny situations and many, many frustrations. Screamer#FAIL tells some stories about this clash of ages. It's the report of a surviver, of somebody who haswasted invested a lot of energy fighting corporate windmills of our times.
And here the story begins: "The Bus"...
Waterfall is the classical way to do software, it has been used for centuries (well, at least it feels like that). The approach is simple, it's an idea taken from manufacturing and follows the thinking of the industrial revolution: the assembly line. It requires to have separate groups of specialists who take some input, process it and pass it on to the next group. Each group tries to reduce the time it takes to get an input and pass it to the next group. Each group invests time and effort improving the quality of it's output. For a manager, this looks perfect. Optimizations at each step, it's measurable, transparent and responsibilities are clear. What else could you wish? That's why this kind of process was adopted in software development and is still widely used in most companies.
With time, waterfall started to morph into a sort of Frankenstein of the software development world. Managers were adding more and more metrics (they call them KPI's) to optimize it, to squeeze every bit of efficiency they could find in each of the phases. They felt that something was wrong and they tried to fix the symptoms they were finding. They even came with new ideas like overlapping those phases and having people to work on many of those at the same time to further increase efficiency. And that didn't help. Projects were still late, they still did not meet the expectations of the customers.
But people working in those processes where the ones who suffered the most. They knew that it was all going in the wrong direction. They felt that they were wasting their times, that they were not using their skills, that they were just pushing some buttons and could not use their instincts and their skills to move things forward. That was the birthplace of the "Agile Manifesto" and the start of a movement which today sells training and certifications to managers who still don't understand what they are buying. One of those products being sold today is called Scrum (tm). Gurus say that it's a framework, and what they mean by that is that you have to understand what you are doing instead of just following what people or books tell you to do.
Scrum talks about self-organization, about working in short time-slices (they call them sprints), about organizing the work to do in one single master list called a backlog. They say that you have to scrap your big master plan and start planning as you go. They say that you have to start using your brain and following what you believe is right. Scrum is a brand for all the ideas and principles behind the Agile Manifesto and the Lean movement. And it sells pretty good.
The ideas behind Agile and thus behind Scrum represent the thinking of the information age. Shared economy, empowerment, transparency, intrinsic motivation and many others. And here is where the tragedy starts. These ideas are completely opposite to the ones which currently build the culture of corporations. Trying to get enterprises to understand and follow these principles and these ways of working is the challenge of our generation, and it generates funny situations and many, many frustrations. Screamer#FAIL tells some stories about this clash of ages. It's the report of a surviver, of somebody who has
And here the story begins: "The Bus"...
Preface
Scrummer#FAIL is rather a tragedy than a blog. It's the authors attempt to share his experiences about things he has seen and how an ideal world should NOT look like. This tragedy is a collection of bits an pieces from real project life. Names were changed, but the stories are real. Sad but true!
Please give me all your feedback - the texts are not edited, they are just a raw dump of my memories. They may be an accurate description of what really happened, but it's just the state which was (sometimes painfully) forged in my brain. In some cases I had to write the stories as a means of protecting my mental health, to expunge the emotions and the frustration out of my body. So please beware that you may get some of that thrown over you, and I don't want to hear complains!
Ah, and please help me correcting grammar and typos - that's not my strength either. Ok, now let me start dumping all what I have in my brain.
Now go and read the Introduction.
Please give me all your feedback - the texts are not edited, they are just a raw dump of my memories. They may be an accurate description of what really happened, but it's just the state which was (sometimes painfully) forged in my brain. In some cases I had to write the stories as a means of protecting my mental health, to expunge the emotions and the frustration out of my body. So please beware that you may get some of that thrown over you, and I don't want to hear complains!
Ah, and please help me correcting grammar and typos - that's not my strength either. Ok, now let me start dumping all what I have in my brain.
Now go and read the Introduction.